There are two phases of the transportation timeline for the Nā Pua Makani Wind Farm: roadside improvements and equipment transport.
PHASE ONE: August 5 to October 12
● Road-side improvements along Kamehameha Highway
● Both daytime and nighttime hours
PHASE TWO: From October 14 to November 26
● Transport of Nā Pua Makani Wind Farm equipment
● Nighttime hours
We invite you to check back here for real-time notifications of traffic along the project route.
Mahalo for your patience and kōkua.